Practice 06 / Specialised Technical Consulting

How a project runs

Six sequential phases, each ending in a formal milestone review. The client decides at every gate whether to proceed, and nothing moves forward without written approval.

Project process

Phases, deliverables and gates

PhaseWorkKey deliverablesGate
01Initial assessmentRequirements, high-level feasibility study, waste chemistry reviewFeasibility report; requirements documentApproval to proceed
02Detailed assessmentDetailed plant design, implementation plan, financial modelPlant design; implementation plan; financial modelSign-off on design and model
03Manufacture and site prepEquipment manufacture, site preparation and civil worksManufactured equipment; site readiness reportApproval to install
04Installation and commissioningInstall and commission equipment, full functionality testingInstallation and commissioning reports; test resultsApproval to operate
05Initial operationStaff selection and training, supervised operation, mass balance settingTraining records; mass balance reportApproval to hand over
06Plant handoverTroubleshooting, operating manuals, maintenance schedulesManuals; maintenance schedules; troubleshooting reportFinal sign-off
Indicative schedule

Roughly two years from first sample to handover

01Initial assessment
1–2 mo
02Detailed assessment
1–4 mo
03Manufacture and site prep
5–10 mo
04Installation and commissioning
3–6 mo
05Initial operation
6–12 mo
06Plant handover
3 mo
StartPhases overlap where the work allowsHandover
NoteTimelines are indicative. Equipment lead times, permitting, site conditions and waste availability all affect the schedule. A detailed programme follows the initial assessment.
Project management

No surprises

End-to-end oversight

We manage the project from assessment to handover and coordinate every contractor and supplier.

Stage-gate reporting

Formal reports at each milestone give your board clear information for decisions.

Regular check-ins

Daily, weekly and monthly progress reviews, with fast escalation of any issue.

Open communication

Transparent reporting on costs, timelines and project health.

Risk management framework

  • Structured risk assessment at initiation, updated at every stage gate, covering technical, financial, regulatory and schedule risk.
  • Mitigation strategies written for each specific risk and assigned to a responsible party.
  • Documented contingency plans for high-probability scenarios.
  • Risk register reviewed at every major milestone, with emerging risks escalated promptly.